Multi-run meter station under a wide Texas sky

← Selected work

Meter station / Civil + mechanical

Final Delivery
Meter

Station

Abilene, Texas

March 15 – June 1, 2026

Zero recordables

The assignment

A new connection.
Built in motion.

Vector built a new 24-inch final delivery point meter station in Abilene, Texas, establishing a natural gas connection for a new data center load. Multiple parallel meter runs were sized for required throughput and maintenance isolation while the station took shape inside an active, shared construction site.

Meter size

24

inches / multi-run

Crew size

19

OSHA recordables

Zero

Weld inspection

100%

X-ray

Scope of work

Fabricated in-house.

Installed in the field.

Field crew guiding pipeline equipment into position

Meter station

New 24-inch final delivery point station with multiple parallel meter runs and additional small meters for auxiliary equipment.

Civil / trenching

In-ground header trenching across a congested site, including dewatering through repeated rain events and coordination around shared access.

Fabrication + valves

Full yard and field fabrication, field dimensional verification, and installation of Bettis actuated valves tied into the station’s emergency shutdown system.

Field execution

The site
never stopped
moving.

Fabrication began in the Vector yard on March 15 to get ahead of the schedule. Crews mobilized April 15 and completed the station June 1 while coordinating with data center contractors, an adjacent wind farm, scheduled blasting shutdowns, shared access, and changing ground conditions. Every weld received 100% X-ray inspection; repairs were resolved without a cutout, and field dimensional checks caught issues before installation.

Multi-run meter station under a wide Texas sky Field crew guiding pipeline equipment into position